The work is progressing well at the Kenmuir Arms, and then end is in sight! The building and grounds are going to look fantastic and we can’t wait to showcase to our Community and further afield. The work is scheduled…
Tenancy Opportunity – Kenmuir Arms
We are now at the stage of advertising for a tenant to run and manage the Kenmuir Arms Hotel in the village. The renovations will be completed by the end of October. We are using Graham and Sibbald, Property Consultants…
BUSINESS OPPORTUNITY
Are you forward thinking & dynamic? Are you looking for a new business opportunity? New Luce Community Trust are seeking to find enthusiastic tenants to run and manage the Kenmuir Arms Hotel in the village on a lease basis {31…
Kenmuir Arms Project
We are now into month 9 of the refurbishment works, and it is all starting to take shape now. The upstairs rooms are all up, along with the Tenants flat all partitioned off. Downstairs the toilet areas are all created,…
Kenmuir Arms Update – Oct 21
We are now into month 6 of the renovation works on the Kenmuir Arms. We are now starting to see real progress within the building, with the upstairs flat starting to take shape, along with blockwork for the toilets and…
Kenmuir Arms Update
We are into month 3 of the renovation works, which has thrown up several unexpected additional works to be carried out due to rotten timbers and ceiling joists and of course the appearance of bats! However Luce Bay Plant Hire…
And so it begins…
We are delighted to announce the long awaited work on the Kenmuir Arms has started. The refurbishment and renovation works will take around 50 weeks to complete. Luce Bay Plant Hire have been appointed as the main contractors. We will…
Kenmuir Arms Update
Full planning permission and building warrant permissions have now been approved by the Local Authority, meaning that once a contractor has been selected we can start on the refurbishment works and get this building looking great once again! Tender paperwork…
Kenmuir Arms Update-August 2020
Phase 1 of the refurbishment of the Kenmuir Arms has taken place, and saw the building being stripped back to the structural walls. Phase 2 which is the main refurbishment works hopes to get underway very soon, the building warrant…
Kenmuir Arms – Update
There has been a lot of work going on behind the scenes with this project. Planning permission has now been granted unconditionally for the required works and we hope to have the building warrant submitted by the end of the…